Status on : adopted by the Council; Parliament's final vote expected 23 November 2026.

Legislative timeline
Guide: authorisation procedures

The decentralised procedure timetable, explained day by day

The decentralised procedure (DCP) authorises a medicine in several EU and EEA Member States at once when it is not yet authorised in any of them. Its legal timetable is short, 120 days plus 90 days under Article 28 of Directive 2001/83/EC, but the calendar time is driven by the clock-stop, the national phase and the slot you can get with a reference Member State. This guide follows the procedure from slot booking to national authorisation, explains who does what, lists what typically stops the clock, and compares the route with mutual recognition and the centralised procedure.

Legal basis and who does what

The DCP is set out in Article 28(3) to (5) of Directive 2001/83/EC. The applicant submits an identical dossier to every Member State where it wants an authorisation and asks one of them to act as reference Member State (RMS). Within 120 days of receiving a valid application the RMS prepares a draft assessment report, a draft summary of product characteristics (SmPC), labelling and package leaflet, and sends them to the concerned Member States (CMS) and the applicant (Article 28(3)). The CMS then have 90 days to approve those documents (Article 28(4)); once the RMS records the agreement and closes the procedure, each Member State adopts its national decision within 30 days (Article 28(5)).

The directive gives the skeleton. The day-by-day milestones come from the Member States' standard operating procedure for the DCP and the best practice guide for the decentralised and mutual recognition procedures, both published by the Co-ordination Group for Mutual Recognition and Decentralised Procedures (CMDh). The glossary entries on the RMS and the CMS describe the two roles: the RMS assesses and co-ordinates, the CMS comment and must agree, and a CMS can only block the outcome on grounds of a potential serious risk to public health.

The route is open to any product outside the mandatory scope of the centralised procedure in Regulation (EC) No 726/2004. In practice it is the standard route for generics, hybrids and well-established use applications.

Before Day 0: slot, pre-submission meeting and validation

The procedure cannot start until the RMS has a slot for it. Each agency sets its own rules for allocating slots and publishes them in the CMDh compilation of national recommendations for requests to act as RMS. Most allocate first come, first served using the common CMDh request form; some want the request two or three months before submission, others accept bookings up to two years ahead. The SOP recommends a pre-submission exchange with the RMS at least two months before submission, and the CMDh publishes recommended submission dates each year so that Day 210 does not fall at a weekend or in a holiday period.

Once submitted to all Member States, the validation period is 14 days and starts when the RMS and every CMS have received a technically valid application. The RMS completes the main validation against its checklist and the CMS limit themselves to the points on the CMS checklist. A positive validation is recorded in the CTS tracking system and the RMS confirms the start of the procedure and the timetable. Common reasons for a delayed Day 0 are an application form that does not match the dossier, missing proof of fee payment in a CMS, legal basis questions and incomplete module 1 documents such as the pharmacovigilance system summary.

Assessment step I: Day 0 to Day 120

DCP assessment step I milestones
DayWhoWhat happens
Day 0RMSStart of the procedure confirmed to CMS and applicant after a 14-day validation period.
Day 70RMSPreliminary assessment report with comments on the SmPC, labelling and leaflet sent to CMS and applicant.
Day 100CMSComments to the RMS, the other CMS and the applicant, marked as potential serious risk to public health or other concern.
Day 100 to 105RMS and CMSThe RMS consults the CMS on the comments raised and talks to the applicant.
Day 105RMSIf all agree the product is approvable, the RMS may close the procedure and move to the national step. If not, the RMS stops the clock and sends the applicant the request for supplementary information.
Clock-stopApplicantResponses due within 3 months, extendable by 3 months; 6 months at most, after which the RMS restarts on the data available or asks for withdrawal.
Day 106RMSClock restarts on receipt of the responses.
Day 120RMSDraft assessment report, draft SmPC, leaflet and labelling sent to CMS and applicant. This is Day 0 of the 90-day period in Article 28(4).

Two details of step I surprise first-time applicants. The procedure can close at Day 105: for a straightforward generic with no objections, the assessment ends before any clock-stop and the national step follows. And the applicant may send the RMS a draft response during the clock-stop, so the RMS can flag whether the main concerns are answered before the final response goes to every CMS.

Assessment step II: Day 120 to Day 210

DCP assessment step II milestones
DayWhoWhat happens
Day 145CMSComments on the draft assessment report (Day 25 of the 90-day period). Remaining potential serious risks must be stated now.
Day 150RMSConsultation with the CMS on the comments; outstanding issues go to the applicant if there is no consensus.
Day 160ApplicantWritten clarification, including any revised product information.
Day 180RMSReport on the applicant's response and updated draft SmPC, leaflet and labelling to the CMS (Day 60 of the 90-day period).
Day 195RMS, CMS, applicantBreak-out session or hearing if potential serious risks remain (Day 75). Teleconferences often take place around Day 195 to 205.
Day 205CMSLast day for new comments; changes to the product information after Day 205 are exceptional.
Day 210RMSClose of the procedure if there is consensus, or referral to the CMDh (Day 90 of the 90-day period).

The procedure can close at any point in step II once every CMS agrees the product is approvable; Day 210 is the latest, not the target. At Day 210 the RMS closes a positive procedure with the final assessment report and agreed texts, or closes a negative one if it concludes the product is not approvable, in which case there is no referral and each Member State refuses nationally. If a CMS maintains a potential serious risk to public health at Day 210, the RMS refers the points of disagreement to the CMDh within seven days under Article 29(1) of the directive.

The CMDh then has 60 days to reach agreement (Article 29(3)). If it does, the RMS records the agreement and closes the procedure at Day 270. If it does not, the matter goes to the Committee for Medicinal Products for Human Use for scientific arbitration under Articles 32 to 34, and the Member States that agreed with the RMS may, at the applicant's request, authorise the product without waiting for the outcome (Article 29(6)). The glossary entry on referrals sets out the arbitration route.

The national phase: 30 days to a national authorisation

Closing the procedure is not the same as holding a licence. Under Article 28(5) each Member State adopts its national decision within 30 days of the RMS recording the agreement. That clock is conditional: the CMDh best practice guide expects the applicant to submit high-quality national translations of the SmPC, leaflet and labelling, with mock-ups where needed, no later than seven calendar days after the procedure closes. Member States may only make linguistic changes to the agreed texts and may add national blue-box information. A late or poor translation is the most common reason the 30 days become 60 or 90, and the product cannot be marketed in that country until the national decision issues.

The national phase is also where the common renewal date is set, usually five years after the end of the procedure. Regunaut Atlas keeps these dates, obligations and fees per product and market on one timeline.

What typically stops the clock, and for how long

Formally, the clock stops once, at Day 105, and only if there is no consensus. The default response period is three months, which the applicant can extend by a further three months on a justified request sent to the RMS at least one month before the deadline; six months is the ceiling, after which the RMS either restarts the procedure on the information available or asks the applicant to withdraw in all Member States. In practice the time to approval is usually 12 to 18 months from Day 0, and the following issues account for most of the clock-stop time.

  • Quality questions on the active substance, in particular an active substance master file whose closed part raises questions that the ASMF holder, not the applicant, must answer within the same period.
  • Bioequivalence: the reference product, the study design or a borderline result. The glossary entry on bioequivalence covers the usual objections.
  • Divergent national positions on the product information, especially where the reference product's national SmPCs differ.
  • User consultation of the package leaflet that was not performed or not bridged.
  • Legal basis and data protection: whether the reference product's protection periods have expired in every CMS, and whether the generic or hybrid basis is the right one.
  • Orphan similarity, which the applicant must check before submission, during the clock-stop and again in the national phase.

The response should answer each question in order and update every affected module, because the RMS writes the draft assessment report from it between Day 106 and Day 120. New studies are not accepted after that, so the clock-stop is the one place to put complete data in.

How to choose a reference Member State

The RMS writes the assessment report that every CMS relies on, so the choice shapes the whole procedure. Four practical criteria matter most.

  • Slot availability. Agencies differ widely in how far ahead they are booked and how they allocate slots; the CMDh compilation of national recommendations lists each agency's rules and contact points, and some publish free capacity monthly.
  • Experience with the product type. An RMS that has assessed the same active substance or dosage form will have settled positions on the product information and on the typical objections, which shortens step I.
  • Fees and language. RMS fees are usually higher than CMS fees and vary considerably; the RMS also sets expectations on the language of the response and the quality of the English texts that all CMS translate from.
  • The later procedures. The RMS of the DCP is the RMS for every later variation, renewal and repeat-use procedure on the same authorisation, so the agency's performance on variations matters as much as its speed on the initial assessment.

A pre-submission exchange with the intended RMS, at least two months before submission, tests these assumptions and fixes the timetable. Scientific advice on a contentious point, such as a biowaiver or a hybrid legal basis, before the slot is booked avoids spending the clock-stop on it.

DCP compared with MRP and the centralised procedure

The three EU routes compared
RouteWhen it appliesLegal timetableDecision
Decentralised (DCP)Product not yet authorised in any Member State; applicant chooses the RMS and CMS120 days for the RMS draft report, 90 days for CMS agreement (Art. 28(3) and (4)), plus the clock-stop; CMDh referral of 60 days if neededNational authorisations within 30 days of closure, one per Member State
Mutual recognition (MRP)Product already authorised in one Member State, which becomes the RMS; also used for repeat-use waves after a DCPRMS updates the assessment report within 90 days; CMS recognise within 90 days (Art. 28(2) and (4)), with comments at Day 50 and closure at Day 90National authorisations within 30 days of closure
CentralisedMandatory for the Annex of Regulation (EC) No 726/2004; optional for new active substances and products of interest to EU healthCHMP opinion within 210 days of a valid application, with clock-stops at Day 120 and Day 180 (Art. 6(3)); Commission decision followsOne Commission decision valid in every Member State

The glossary entry on MRP covers the mutual recognition route in more detail. The trade-off is control against coverage: DCP and MRP give one national authorisation per country, which can be varied, renewed or withdrawn market by market, while the centralised route gives a single licence with one product information text for the whole EU. For a generic portfolio the DCP, followed by repeat-use MRP waves, remains the usual pattern.

The agreed 2026 EU pharma package keeps the national procedures, the reference Member State model and the CMDh, and sets the centralised assessment at 180 days instead of 210 in the regulation half of the package. Our overview of the new pharmaceutical regulation covers the centralised changes, and the legislative timeline tracks when the new texts will apply; article numbers and day counts for the national procedures should be checked against the act once it is published in the Official Journal.

Common questions

The DCP timetable: what teams ask

How long does a decentralised procedure take in calendar time?

The legal assessment time is 210 days, but the clock usually stops at Day 105 for up to three months, extendable to six, and the national phase adds at least 30 days after closure. Twelve to eighteen months from Day 0 to the first national authorisation is typical for a generic; add the wait for an RMS slot before Day 0.

Can a DCP finish before Day 210?

Yes. If the RMS and all CMS agree at Day 105 that the product is approvable, the RMS may close the procedure there. During step II the procedure can close at any time before Day 210 once consensus is reached. Day 210 is the latest closing date, not the normal one.

What happens if a CMS still objects at Day 210?

A CMS can only block on grounds of a potential serious risk to public health. If it maintains one at Day 210, the RMS refers the disagreement to the CMDh within seven days under Article 29 of Directive 2001/83/EC. The CMDh has 60 days to reach agreement; if it fails, the matter goes to the CHMP for arbitration, and Member States that agreed with the RMS may authorise the product in the meantime at the applicant's request.

When are the national translations due?

The CMDh best practice guide expects high-quality national translations of the SmPC, package leaflet and labelling, with mock-ups where needed, no later than seven calendar days after the procedure closes. Each Member State then has 30 days to grant the national authorisation under Article 28(5), subject to receiving acceptable translations.

How do we get an RMS slot?

Use the common CMDh request form and follow the rules of the agency you want as RMS, published in the CMDh compilation of national recommendations for requests to act as RMS. Most agencies allocate first come, first served; some need the request two to three months ahead. Agree the timetable with the RMS before submitting.

Does the 2026 EU pharma package change the DCP timetable?

The agreed directive keeps the decentralised and mutual recognition procedures, the reference Member State role and the CMDh. The headline timing change in the package is in the regulation, where the centralised assessment is set at 180 days instead of 210. The exact day counts for the national procedures in the published act should be checked once it appears in the Official Journal.

Sources

Article numbers refer to the Council's position at first reading of 28 September 2026 (ST 7106/2/26 REV 2 for the directive, ST 7105/2/26 REV 2 for the regulation), which reflects the political agreement of December 2025. Numbering may change in the act published in the Official Journal.

  1. EUR-Lex: Directive 2001/83/EC on the Community code relating to medicinal products for human use, consolidated text, Articles 27 to 34
  2. CMDh: Decentralised Procedure, Member States' Standard Operating Procedure (CMDh/078/2005, Rev. 11, January 2023)
  3. CMDh: Best Practice Guide for Decentralised and Mutual Recognition Procedures (CMDh/068/1996, Rev. 14, April 2022)
  4. CMDh: National recommendations for requests to act as Reference Member State in the DCP (CMDh/020/2009, Rev. 36, January 2026)
  5. CMDh: Procedural guidance on applications for marketing authorisation in the DCP and MRP
  6. EUR-Lex: Regulation (EC) No 726/2004 laying down Community procedures for the authorisation and supervision of medicinal products, Articles 3 and 6
  7. Council of the EU: Position at first reading on the Directive on the Union code relating to medicinal products for human use, adopted 28 September 2026 (ST 7106/2/26 REV 2)
  8. Council of the EU: Position at first reading on the Regulation laying down Union procedures for the authorisation and supervision of medicinal products, adopted 28 September 2026 (ST 7105/2/26 REV 2)
  9. Council of the EU: 'Pharma package': Council and Parliament reach a deal (press release, 11 December 2025)
  10. Council of the EU: The pharma package, new EU rules on medicines (policy page)
  11. European Commission: Reform of the EU pharmaceutical legislation
  12. EUR-Lex: Procedure 2023/0132/COD, Directive on the Union code relating to medicinal products for human use (COM(2023) 192)
  13. EUR-Lex: Procedure 2023/0131/COD, Regulation on Union procedures for the authorisation and supervision of medicinal products (COM(2023) 193)

Plan the next DCP with the dates and fees in one place

Atlas keeps procedure milestones, national decisions and renewal dates per market on one timeline. Fee Calculation estimates the RMS and CMS fees before you commit.

Book a procedures walkthrough

30 minutes on your pipeline: which route fits each product, what the RMS and CMS will cost, and how Regunaut tracks the milestones.

Book a demo

Ask Workbench yourself

Put a procedure question to Workbench and get an answer that cites the directive and the CMDh guidance.

Try for free
Book a 30-min walkthrough